#

Press Section

Contract journal, 23 November 2005

Breaking the mould

MAN ON A MISSION: Architectural Cladding Association chairman Stephen Maddelena is determined to prove to contractors the time and cost savings possible with precast.

Precast's share of the cladding market is growing, but not as fast as Architectural Cladding Association chairman Stephen Maddalena would like. He tells Will Mann why dyed-in-the-wool attitudes are holding back its wider uptake.

The economics of precast cladding add up to anyone with a basic grasp of a balance sheet, but Stephen Maddalena still has a job selling it to the wider construction industry.

"We're fighting against the traditional way of building things," says the managing director of precaster Marble Mosaic. "Architects want to design every job so that one stone has to be laid on top of the other, and those are the only kind of jobs that most main contractors know how to build."

Changing times

Change is in the air though. "We're starting to see contractors who are more switched on to precast's benefits," says Maddalena, who chairs the Architectural Cladding Association (ACA).

"The likes of Sir Robert McAlpine, Bovis Lend Lease and housebuilder St George - where the construction team is ex-Lovells - all use precast widely.

"We are currently working on a project in Piccadilly Circus where there are obviously major access issues and the main contractor told the client: 'We won't build this unless it's precast.'"

Precast's share of the cladding market is still relatively small, probably between £50m and £100m, which is only around 2% to 3% of the whole cladding market. Growing that share is Maddalena's mission at the ACA.

Members first

The association is one of construction's smaller trade bodies, with only three other members besides Marble Mosaics: Techrete (UK), Trent and Belgian firm Decomo. Redland Precast of Hong Kong is an international member.

But the slim membership is partly due to the exacting standards set by the ACA; aspiring members must be not only manufacturers, but also designers, constructors and hauliers. Demonstrating the point, outside Marble Mosaic’s Weston-super-Mare factory there are three lowloaders, three 30ft trailers, plus three other, shorter trailers. For bigger jobs, 40-footers are hired in, Maddalena adds.

The £6m turnover Marble Mosaics was founded 100 years ago in Bristol, but in the past decade or so, the company has gradually spread it's workload around the country. Funnily enough, Maddalena's first job in the capital was the facade for CJ's own offices - and it still looks in pretty good nick, 20 years on.

At present, key markets for precasters are residential apartment blocks, student accommodation, commercial offices and retail centres.

"The rebirth of the town centre has been great for us," says Maddalena. "Retail centres lend themselves to precast because speed of construction is of the essence for the client, and they want minimal disruption to the surroundings. They tend to be large work packages too, and there are quite a few more in the pipeline.

"Precast cladding generally works best on schemes with 500m2 of facade. Below 250m2 and you're not going to get economies of scale."

Cladding costs

The cost of precast cladding starts at around £275/m2 'on the wall' for recon (reconstructed stone) panels, give or take 10%, says Maddalena. Brick- or tile-faced panels are around the £300 mark, with high-quality stone like Portland in the region of £400/m2 to £500/m2.

"But the point is," he adds, "this doesn't factor in savings on the other trades necessary when the facade is constructed in situ. You won't need any bricklayers, which are a scarce resource at the best of times.

"And you won't need any scaffolding either - and in places like the City of London that's very important to both clients and main contractor. They want precasters who can come in on a JIT basis."

This means the precaster has to take on a fair degree of risk. "Our yard in Weston is a buffer between my economic production and deliveries to site," Maddalena explains. "The lead-in we typically require is eight weeks for design development, then 12 weeks for the manufacturing. With stone there's a longer lead-in, if we're sourcing Chinese granite, for example, it might take us three months to obtain the materials.

"But we can give a main contractors certainty of supply, which they might not get with bricklayers."

Looking ahead, Maddalena sees plenty of scope for further technological advance in the precast cladding sector.

"In future, there's no reason why we shouldn't be casting in services," he says. "We're already taken a step towards that by casting in air vents.

"We're also supplying more and more panels fitted with insulation, which has been driven by Part L.

"And the manufacturing process itself is becoming more sophisticated; Techrete has just invested £3.5m in a new UK plant that features an automotive industry-style Carousel system."

Geared for delivery

The precast cladding sector is geared up to deliver if the wider industry is prepared to give it a chance.

"A lot of our business is secured by negotiation with those who realise the direct and incidental benefits of precast cladding," says Maddalena, "but not enough contractors evaluate what we have to offer early enough. We are presented with a number of schemes that have been designed for traditional construction, and we then have to adapt them for precast.

"But if we'd been involved earlier, the scheme would have been more buildable, cheaper and safer.

Cladding Bristol fashion

A few miles up the M5 from Marble Mosaic’s Weston-super-Mare factory, there's a classic example ofthe kind of project Maddalena would love to do much more of.

The office development. in a busy commercial area of Bristol, was designed specifically for precast by architect Stride Treglown, largely in recognition of the need for a speedy construction programme and the potential for access problems with an in situ scheme.

Wates is constructing the office for developer RokEagle and the facade features 210 precast panels.

The recon panels have a coarse textured surface below second floor level, and a smooth acid-etched finish above, giving a Portland stone 'look' - though Maddalena points out the end result is not porous and will weather much better than natural stone. The panels also have insulation fixed to their internal face to enhance their thermal performance.

Thirty-eight of the panels have a framed and glazed window cast into a 5.75m x 2.5m aperture, and the risk of the glass breaking during transportation is carried by the precaster, Maddalena reveals. The windows are fitted into the aperture by a glazing contractor, who sets up in the corner of Marble Mosaics' yard.

"We did have some problems with this, mainly because the framing system wasn't fitting into the panel apertures," says Maddalena, "but in some respects, this demonstrates the advantage of precast - we were able to sort the problem out in the yard, rather than when it was on the building."

Wates has been installing between four and six panels-a-day on average, mostly using the site's 80t tower crane. The only facade the tower crane could not reach was the north elevation, which meant bringing in a mobile crane with a 4t lifting capacity. This caused the only disruption to the surroundings during the facade installation, forcing the closure of the adjacent road for a day.

The panels are attached to the building via bolted connections, which engage in channels in the main concrete frame. Their weight is supported by stainless steel corbels, which are cast into each panel.

The bearing points of the panels are adjacent to the building's structural columns. This dispenses with the need for midspan loading which, as Maddelena points out, would be necessary with brickwork or blockwork.

Once the panels are on the building, the facade is weatherproofed with the application of polyethylene cord in the 18mm to 20mm gaps between the panels, then a mastic seal on top. This is applied by abseilers.

"We've only started using them relatively recently," says Maddalena, "and they're quite expensive compared to the window cleaner cradles we used before. But they're very quick, which is the key factor on a site with limited access. "

 

#